IAS 11 Construction Contracts

IAS 11 Construction Contracts
The objective of this Standard is to prescribe the accounting treatment of revenue and costs associated with construction contracts. Because of the nature of the activity undertaken in construction contracts, the date at which the contract activity is entered into and the date when the activity is completed usually fall into different accounting periods. Therefore, the primary issue in accounting for construction contracts is the allocation of contract revenue and contract costs to the accounting periods in which construction work is performed.
This Standard shall be applied in accounting for construction contracts in the financial statements of contractors.
A construction contract is a contract specifically negotiated for the construction of an asset or a combination of assets that are closely interrelated or interdependent in terms of their design, technology and function or their ultimate purpose or use.
The requirements of this Standard are usually applied separately to each construction contract. However, in certain circumstances, it is necessary to apply the Standard to the separately identifiable components of a single contract or to a group of contracts together in order to reflect the substance of a contract or a group of contracts.
Contract revenue shall comprise:
(a) the initial amount of revenue agreed in the contract; and
(b) variations in contract work, claims and incentive payments:
(i) to the extent that it is probable that they will result in revenue; and
(ii) they are capable of being reliably measured

Contract revenue is measured at the fair value of the consideration received or receivable.
Contract costs shall comprise:
(a) costs that relate directly to the specific contract;
(b) costs that are attributable to contract activity in general and can be allocated to the contract; and
(c) such other costs as are specifically chargeable to the customer under the terms of the contract.

When the outcome of a construction contract can be estimated reliably, contract revenue and contract costs associated with the construction contract shall be recognised as revenue and expenses respectively by reference to the stage of completion of the contract activity at the end of the reporting period.
When the outcome of a construction contract cannot be estimated reliably:

(a) revenue shall be recognised only to the extent of contract costs incurred that it is probable will be recoverable; and
(b) contract costs shall be recognised as an expense in the period in which they are incurred.

When it is probable that total contract costs will exceed total contract revenue, the expected loss shall be recognised as an expense immediately.

Comments

Popular posts from this blog

CA Info - industrial training

Hi Friends, Here is the list of approved insitutions eligible for imparting Industrial training Approved Organisations - Eastern Region SIEMENS LIMITED 43 SHANTI PALLY E.M.BY PASS CALCUTTA 700042 CITI BANK N.A. TATA CENTRE 41,CHOWRINGHEE ROAD CALCUTTA 700071 RECKITT & COLMAN OF INDIA LTD 41,CHOWRINGHEE ROAD CALCUTTA 700071 BRITANIA INDUSTRIES LTD . 14, TARATALA ROAD CALCUTTA 700088 ICI INDIA LTD 34, CHOWRINGHEE ROAD CALCUTTA 700071 GRASIM INDUSTRIES LTD. INDUSTRY HOUSE 14TH FLOOR, 10, CAMAC STREET KOLKATA 700017 AMERICAN EXPRESS BANK 21, OLD COURT HOUSE STREET CALCUTTA 700001 BALMER LAWRIE CO. LTD 21, NETAJI SUBHAS ROAD CALCUTTA 700001 INDIAN OIL CORPORATION LIMITED 2,GARIAHAT ROAD(S) DHAKURIA CALCUTTA 700068 SRF LIMITED EXPRESS BUILDING 1ST FLOOR BAHADUR SHAH ZAFAR MARG NEW DELHI 110002 INDIAN RAYON AND INDUSTRIES LTD RISHRA HOOGHLY 712249 PEPSI-COLA INDIA MARKETING COMPANY SREE MANJURI BLDG. SUITE NO.6 , 1ST FLOOR 8/1, MIDDLETON ROW CALCUTT...

Economic Survey 2013 Highlights

Chief Economic Advisor Raghuram Rajan tabled his first ever Economic Survey. Key features of the Survey are: GDP growth for 2012-13 is expected at 5% GDP growth for 2013-14 is expected at 6.1% to 6.7% The Average WPI Inflation has come down from 8.9% in 2011-12 to 7.6% in 2012-13 The Average CPI Inflation has increased from 8.4% in 2011-12 to 10.0% in 2012-13 Gross Fiscal Deficit has come down from 5.7% of GDP to 5.1% of GDP Revenue Deficit has come down from 4.3% of GDP to 3.5% of GDP The trade deficit increased to US$ 189.8 billion (10.2 per cent of GDP) in 2011-12 as compared to US$ 127.3 billion (7.4 per cent of GDP) during 2010-11. Current account deficit seen at 4.6% for 2013-14 Overall global economic environment remains fragile Gold imports is key contributor to inflation, imports need to be curbed LPG and Diesel prices need to be increased in line with global rates, oil subsidy is a key risk

Vikash Goel - Introduction

Hello People, Welcome to my Blog Please pardon me if u find this blog a bit unconventional, unusual and out of place. To be honest, m not a blogger and this is my Debut as far as Blogging is concerned. I am a simple, average guy from Kolkata, India. I am a CA, MS Finance, CFA (ICFAI, India), Diploma in Business Management, Bachelor of Commerce. Meanwhile for a quick look about me, visit the link below, (its become a little outdated as of now but still enough to give an idea about me) http://www.freewebs.com/vikash_goel/ www.vikashgoel.com Catch ya soon